Project Experience
Project Type:
Pile and Pipe
Construction
- Installed pipe-piles, pipe-racking and
flare stack for gas plant compressor station.
- Installed guy-wire anchors for flare stack.
- Pipe pile construction consisted of
concrete-filled pipes with load capacities of 200 kilopascals/cm.
- Total quantity of units-
20 - 12", 40 - 10", 60 - 8",
120 - 5" pipes.
- Depths drilled-
- Drilling overburdens up to 100'
- Seeding into bedrock up to 20'
|

Various sizes of pipe
used for pile installation

Down - hole view of
piling borehole
|
Large Scale
Retaining walls (South LRT Extension Project, Edmonton Alberta)
-
Excavation and construction of retaining walls
- Shotcrete Preparation and
management of multiple stage project
- Drilled to various depths
for anchor and soil nail installation.
- Various drill rigs used
for hole preparation-
- Anchors
and soil nails post tensioned for retaining wall integrity
See also
Construction Services |
|
|
|
|
|
|
|
South LRT Extension Project |
|
Completed retaining walls and anchor systems Edmonto, Alberta |
|
|
|
|
|
|
|
|
|
|
|
|
South LRT Extension Project |
|
Multi level retaining wall Edmonton, Alberta |
|
|
|
|
|
|